2006:
- March: Project´s kick-off
- September: ground-breaking ceremoy (after 6 months of planning)
2007:
- January: laying of the foundation stone
- May: topping-out ceremony (2 weeks ahead of schedule)
- October: pharmaceutical interior fittings are finished
- December: acceptance of construction work after 15 months of construction & bringing into service the raw materials storage
2008:
- April: Manufacturing License only 25 months after project´s kick.off & bringing into service sampling & weighing center
- June: filling of first production charge on a new filling line
- September: transfer of existing equipment - first phase of the move
Outlook:
2010:
- July 2010: start of production on a further, new filling line
- September 2010: start of the second phase of the move
2011:
- May 2011: finishing all transfer projects