Milestones of the project

2006:

  • March: Project´s kick-off
  • September: ground-breaking ceremoy (after 6 months of planning)

2007:

  • January: laying of the foundation stone
  • May: topping-out ceremony (2 weeks ahead of schedule)

  • October: pharmaceutical interior fittings are finished

  • December: acceptance of construction work after 15 months of construction & bringing into service the raw materials storage

2008:

  • April: Manufacturing License only 25 months after project´s kick.off & bringing into service sampling & weighing center
  • June: filling of first production charge on a new filling line
  • September: transfer of existing equipment - first phase of the move

Outlook:

2010:

  • July 2010: start of production on a further, new filling line

  • September 2010: start of the second phase of the move


2011:

  • May 2011: finishing all transfer projects